Construction · Brick Veneer / Timber Frame
Brick Veneer / Timber Frame Stage Inspections
Brick veneer builds use a timber frame clad in a single brick skin. The sequence runs from the concrete slab through frame, lock-up, PCI, handover, and warranty, each with a distinct inspection window.
Real defects our inspectors have flagged
The build sequence
Every stage in your brick veneer / timber frame build
Each inspection window closes when the next trade starts. Here is the full brick veneer / timber frame sequence: when each stage happens, when to book it, and what you lose if you miss it.
-
- When to book
- Book as soon as your builder confirms the pour date. We inspect one to two days before the trucks arrive.
- Why it matters
- Once concrete is poured, the formwork, footings and reinforcement can never be checked again.
-
- When to book
- Book once the pour date is locked in. One visit covers the pre-pour check and the pour itself.
- Why it matters
- The one chance to check the slab while it is being placed, not after it has set.
-
- When to book
- Book for two or more days after the pour, before your builder starts framing or brickwork.
- Why it matters
- Once the walls go up, nobody can check the slab set-out or catch early cracking.
-
- When to book
- Book the day framing finishes, before any roof cover, cladding or plasterboard goes on.
- Why it matters
- Bracing, tie-downs and lintel sizing can only be checked now.
-
- When to book
- Book once the building is sealed and lockable: roof on, external doors and windows in, before internal fit-out begins.
- Why it matters
- Your last look at flashings, brick ties and waterproofing before the linings hide them.
-
- When to book
- Book as soon as your builder gives you the PCI date and time.
- Why it matters
- Defects documented at PCI are contract corrections. Miss them and they turn into warranty disputes.
-
- When to book
- Book once the builder confirms the PCI defect repairs are finished.
- Why it matters
- Independent confirmation that every PCI item was actually fixed before you accept the keys.
-
- When to book
- Book in good time before your warranty period closes. Your builder or contract sets the exact window.
- Why it matters
- The last window to put settling and movement defects back on the builder before the warranty closes.